A retaining wall for Garden Gulch

Words: Mike AdamsNear the town of Parachute in the mountains of Colorado, Bryan Miller of Miller Walls found himself in the middle of a massive field of slate and rubble, unable to continue up slope and with absolutely no chance of retreat.

Miller had spent three days at the site, trying to determine how — or even if — the retaining wall designed for the Garden Gulch access road could be built. What he didn’t expect was a total time of four hours to traverse three-quarters of a mile, just to escape what he thought was a project walk through.

Garden Gulch is an eight-mile access road to natural gas drilling operations and production facilities on the Logan Mesa. Built in 2006, it reduced truck travel from one hour, 45 minutes, to a 30-minute haul. It was constructed using conventional cut-and-fill techniques and by removal of a number of cliff sections.

This created a huge scree slope of rubble and boulders above the roadway. The unstable slope not only posed a safety hazard to the roadway, but also potentially could impact area waterways. With up to 1,000 trucks moving through per day, closing Garden Gulch was not an option. So, a “mechanically stabilized earth” wall was the obvious choice.

In 2011, a consortium of engineers designed a terraced, segmental retaining wall (SRW) parapet wall, using Diamond Pro Stone Cut wall units supplied by Pavestone LLC. This consortium included Sean Chang, P.E., of Ground Engineering Consultants; Don Armstrong, senior engineer of Anchor Wall Systems; and Lance Carter of Strata Systems.

As the portion of the parapet wall next to the slope was designed to catch any slide material, it was manufactured in a grey concrete, while the front exposed section was manufactured in a custom two-color blend. Despite of the vast experience of the engineering team, the project constraints were such that multiple re-designs were required, many of which were creative in both concept and design. In concert with Miller Wall, solutions included reducing the amount of backfill compaction, as the large compaction equipment would have further destabilized the slope, increasing dangers to the construction crew and making construction a near impossibility.

To date, building the Garden Gulch retaining wall has been considered the toughest installation experience for Miller Wall. Extra crew members were hired to stand watch and provide warning of falling rock. As the mountainside was excavated, the slope became steeper and further destabilized, requiring constant adjustment of machines and crews. An onsite seismic device would register movement of the upper slope and sound a warning siren if the slope moved more than half an inch. When the siren wailed, all work ceased, and everyone quickly moved to designated safe areas.

Due to the location, construction could not begin until after the winter snow melted, but had to be completed prior to the summer monsoons typical for the Colorado Rockies. The site also is remote, necessitating careful planning for daily transportation of workers. To address the accelerated construction requirements, multiple crews worked 12- to 14-hour days for 54 days straight.

When installation outpaced supply, Pavestone LLC was contacted, occasionally requiring Sunday deliveries to fill the void. Despite this, the only delays were due to two rock slides, which shut down the project while the debris was removed from the roadway.

Bryan Miller notes that, had he known then what he knows now, he probably wouldn’t have done this job. “It was one of the most nerve-wracking, high-stress projects we’ve ever been involved with,” says Miller, “but also one of those jobs you can feel proud of having completed.”
Why Belden Brick Has Lasted 140 Years
August 2025

‘Why We’ve Lasted 140 Years’ How The Belden Brick Company’s approach to manufacturing excellence continues to solve modern brick masonry challenges Ask masonry contractor Jason Hauer what separates good brick from great brick, and he’ll tell you about h

Achieving Consistent Mortar Mixes: Key to Successful Masonry Projects
August 2025

Consistency is the cornerstone of quality masonry. A uniform mortar mix is critical for the structural integrity and durability of any project, from a simple brick wall to an intricate stone design. When mortar lacks consistency, it can lead to weak joint

What’s In Your Data Backup Strategy?
August 2025

Your business handles plenty of critical data, and losing it could result in operational downtime, financial losses, and a damaged reputation. For businesses owners, a robust data backup strategy can help you stay resilient and competitive in the fuel mar

Facial Recognition for Masonry Companies
August 2025

Masonry companies face a unique set of challenges. Managing a mobile workforce across multiple job sites requires precision and accountability. CrewTracks recognizes this need and has introduced an innovative facial recognition feature designed to streaml