The Fine Art of Pricing Change Orders

Words: Paul AaronIt's an unfortunate fact: Contractors have to "sell" change orders, even changes requested by the owner that everyone recognizes as valid. It's part of the normal course of project management and it's frustrating. And even if the scope of work is not in dispute, the price can be a different matter.

Assuming unit prices have not been established for additional work, these tips might help you overcome defenses to your price.

Provide a Detailed Description of the Additional Work

  • Use commonly understood terminology that everyone understands. If your work contains trade-specific technical terminology, explain it in simpler terms.

  • Identify exact location of work and be specific to a fault. Use plan page numbers and details, grid lines, phase, building and room numbers, etc.

  • State why additional costs are being passed on. Reference the initiating and confirming document or event. What confirmed the owner's acknowledgement of additional costs?

    Provide a Detailed Price Breakdown

  • Breaking your price down and showing detail of the work sequentially educates the other side. Also, realize that individual line items now become negotiating points.

  • The estimating fact at play here is that the more detailed the cost estimate, the higher the price. An added bonus is we're forced to consider the cost for every detail of the work when we break it down and are less likely to forget small elements.

    Show Contract "Approved" OH and Profit Amounts

  • Include the difference between contract "approved" OH and Profit and your real amount for OH&P in your labor and equipment rates.

  • Agreeing upon unit rates for labor and equipment that are higher than those reflected in the project bid is a must if you hope to recover the difference between what the contract allows for OH and what your actual overhead (G/A) costs are.

    Use Real Invoice Pricing for Material Purchased Specifically for This Change Order Work

  • You won't need to inflate these prices if you have done what we suggested in the previous section.

  • Many contractors pad material costs in an effort to make up their OH costs.

    Use "Retail Shelf Pricing" for Materials Already on Site

  • That is for materials taken out of project inventory.

  • You'll have to replace this material at a price greater than your original purchase price (assuming quantity pricing at bid time and increased materials costs during the course of construction).

    It's never a perfect art or science, but incorporating the above into your change order processes will give you a better chance at winning in the change order game.

  • Why Belden Brick Has Lasted 140 Years
    August 2025

    ‘Why We’ve Lasted 140 Years’ How The Belden Brick Company’s approach to manufacturing excellence continues to solve modern brick masonry challenges Ask masonry contractor Jason Hauer what separates good brick from great brick, and he’ll tell you about h

    Achieving Consistent Mortar Mixes: Key to Successful Masonry Projects
    August 2025

    Consistency is the cornerstone of quality masonry. A uniform mortar mix is critical for the structural integrity and durability of any project, from a simple brick wall to an intricate stone design. When mortar lacks consistency, it can lead to weak joint

    What’s In Your Data Backup Strategy?
    August 2025

    Your business handles plenty of critical data, and losing it could result in operational downtime, financial losses, and a damaged reputation. For businesses owners, a robust data backup strategy can help you stay resilient and competitive in the fuel mar

    Facial Recognition for Masonry Companies
    August 2025

    Masonry companies face a unique set of challenges. Managing a mobile workforce across multiple job sites requires precision and accountability. CrewTracks recognizes this need and has introduced an innovative facial recognition feature designed to streaml